A Resource Requirements Plan Illustrates

Question: Why are activities drawn in a serial relationship in a network diagram?

Answer: From a technical standpoint, the activities must be performed in that sequence.

Question: Resource-limited scheduling attempts a schedule in which the number of resources is limited and?

Answer: the schedule may be extended to keep the resource limits

Question: ______ assists with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.

Answer: Project management information systems

Question: If resources are to be considered in planning, it is necessary to?

Answer: indicate the amounts and types of resources needed to perform each activity

Question: If not enough resources are available for a project, to maintain the same project scope and budget, the project team should?

Answer: delay some activities until the resource is available

Question: In _____, when several activities need the same limited resource at the same time, the activities with the least slack have first priority.

Answer: Resource limited scheduling

Question: When several activities need the same limited resource at the same time, the activities with?

Answer: the least slack have first priority

Question: When planning a project, it is necessary to estimate?

Answer: the types and quantities of resources required to perform each activity.

Question: Activities in a network diagram are drawn in a ______ relationship because, from a technical standpoint, they must be performed in that sequence.

Answer: serial

Question: In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?

Answer: Activities that use the same resource may not be able to occur in parallel to each other