ISDS 3115 Chapter 3 Test Answers And Notes

The three phases involved in the management of large projects are:

ANSWER :  planning, scheduling and controlling.


Which of the following does NOT belong to the planning phase of projection management?

ANSWER :  Monitoring resources


The project organization may be less helpful when:

ANSWER :  the job is familiar to the existing organization


Which of the following is the THIRD level in work breakdown structure (WBS)

ANSWER :  Subtasks in major tasks


Gantt charts are

ANSWER :  planning charts used to schedule resources and allocate time.


Which of the following is NOT part of project controlling?

ANSWER :  sequencing and allotting time to all project activities.


The critical path of a network is the:

ANSWER :  longest time path through the network


How is the EF computed?

ANSWER :  ES + Activity time


Which of these time estimates is NOT used in PERT?

ANSWER :  Standard time


What is the shortest duration required to complete an activity?

ANSWER :  crash time


Which of the following is a limitation of PERT and CPM

ANSWER :  There is the inherent danger of placing too much emphasis on the critical path


Among the following, critical path and slack time analysis MOST help

ANSWER :  pinpoint activities that need to be closely watched


What is the most popular example of specialized software for managing projects?

ANSWER :  microsoft project


Which of the following is not a technique that allows managers to plan, schedule, and control, projects?

ANSWER :  factor – rating method


Which of the following activities are NOT part of project scheduling?

ANSWER :  Make sure all necessary activities are finished in the proper sequence and on time.


Which of the following is an advanatage of PERT and CPM?

ANSWER :  Straightforward concept and not mathematically complex


The most realistic estimate of the time required to complete an activity as referred to as?

ANSWER :  most likely tim


Computerized PERT/CPM reports and charts do NOT include

ANSWER :  probability estimate for on time completion


Which column in microsoft project defines the precidence relationships among the activites?

ANSWER :  predecessors


Which of the following is a direct responsibility of the project manager?

ANSWER :  making sure that the people assigned to the project receieve the motivation, direction, and 

information needed to do their job.


Which of the following is not used for computation in CPM?

ANSWER :  normal time


The latest finish of an activity is:

ANSWER :  min (LS of all immediate following activities)


Which of the following is not true about gantt charts?

ANSWER :  cant charts adequately illustrate the interrelationships between the activites and resources


Donation Page

Support Our Work

Do you appreciate the value this website provides? If so, please consider donating to help keep it running. Your donation will go a long way in helping us continue to provide the same quality of content and services. Every bit helps, and your support is greatly appreciated. Thank you for your generosity.